Building History

skelton 11-02-03 north_wall building_SW

June-July, 2003

    Site Preparation

August, 2003

    Underground Utilities

September 2003

    Main foundations poured. Steel erection started.

October 2003

    Steel erection, roof and exterior skin.

November 2003

    Building sealed to be rain tight.
    Transition to Stanford Power.

December 2003

    Interior walls, Windows, MEP systems

January 2004

    Finish work on exterior walls
    Interior painting, Elevator installation
    Flood on January 1 delays completion and move in

February 2004

    Interior finish work
    Lab casework, hoods, plumbing, etc.
    Office finishes - carpet, lighting
    Community landscaping parties on most weekends

March 2004

    Official Move-in date is March 8!!